Site Operations & 3D Render Portfolio
Projects, Media & Video Coverage
Explore real-world installation logs, 3D high-resolution product models, and official YouTube video demonstrations.
Detailed Case Study
Jindal Steel Power Tamnar Installation
ReErth was commissioned to design and construct a low-resistance grounding loop for JPL Tamnar (Raigarh). The local soil was extremely gravelly, rocky, and highly resistive (650 Ω·m), rendering typical chemical rods ineffective.
Measured Resistivity:650 Ω·m (Rocky Strata)
Electrodes Installed:23 nos (Saumya SEE3070 3.0m)
Final Resistance Achieved:< 0.8 Ω
Complies with IEEE 80 touch and step safety designs.

Grounding Grid Connection - Raigarh SiteLive view of substation grounding strips connected across the transformer grid.
Media & Product Visual Gallery
Real site installation photos & high-precision 3D engineering renders.

Real Site Photos
Earth Pit Excavation & Soil Treatment
Currency Tower, RaipurVerified On-Site Operation

Real Site Photos
Electrode Insertion & Backfill Compaction
BSNL Tower, BilaspurVerified On-Site Operation

Real Site Photos
Substation Grounding Strip Welding
JPL Tamnar, RaigarhVerified On-Site Operation

Real Site Photos
Digital Resistance Meter Field Testing
AIIMS Block B, RaipurVerified On-Site Operation

Real Site Photos
Solar Park Array Grounding Grid
Solar Grid Utility, RaipurVerified On-Site Operation

Real Site Photos
Industrial Earth Chamber Finishing
Shree Ram Heights, RaipurVerified On-Site Operation

Real Site Photos
Saumya Copper-Bonded Electrode Inspection
JSPL Plant, RaigarhVerified On-Site Operation

Real Site Photos
Rooftop Solar Structure Bonding
Commercial Complex, IndoreVerified On-Site Operation

Real Site Photos
High-Voltage Substation Earth Pit Audit
MMRDA Transit, MumbaiVerified On-Site Operation

Real Site Photos
Heavy Substation Bore-Piling Installation
JSPL Mines, RaigarhVerified On-Site Operation

Real Site Photos
Borehole Chemical Backfill Treatment
Rama High Street, RaipurVerified On-Site Operation

Real Site Photos
Earth Pit Digital Resistance Verification
ILS Hospital, Raipur C.G.Verified On-Site Operation

3D CAD Renders
Saumya Copper-Bonded Dual-Pipe Electrode Render
Factory Design CADVerified On-Site Operation

3D CAD Renders
Cirprotec ESE Active Lightning Arrester Dome 3D Model
Architectural 3D RenderVerified On-Site Operation

3D CAD Renders
Mersen Surge Protection Device (SPD) Control Panel
Industrial Panel CADVerified On-Site Operation

3D CAD Renders
Equipotential Copper Busbar Installation Schematic
Substation Spec CADVerified On-Site Operation

3D CAD Renders
Conductive Carbon Concrete Earth Plate Strata Model
Geotechnical DesignVerified On-Site Operation

3D CAD Renders
Solar Grid Utility Grounding Loop Render
Solar Farm Project SpecVerified On-Site Operation
Official YouTube Feature
ReErth Official Video Demonstration
Watch our official video demonstrating Saumya Earthing Electrodes, Cirprotec ESE Lightning Protection Systems, and digital resistance testing procedures directly from our YouTube channel.
Official Corporate Presentation (PDF)16-page official corporate profile detailing CPRI test reports, soil resistivity formulas, and product BoQs.Download ReErth Company Profile 2026 (PDF) →

Official YouTube VideoHD 1080p
Saumya Earthing & ESE Lightning Arrester Field Demonstration
Click to play official video demonstrating resistance testing and earth pit installation.
Verified Channel: @ReErth YouTube